Highway 99 Auxiliary Lanes Project

Highway 99 construction photo Ongoing construction. Nov. 11, 2011 — photo by Karen Laslo

This project was initiated in 1999, after an analysis of traffic accidents showed that 31% of all H99 accidents were occurring in the section between Hwy 32 and East 1st Ave. Phase One, completed in 2010, expanded and improved the on and off ramps at East 1st Ave. Phase Two will add 2 lanes on the inside of the existing roadway within Bidwell Park, upgrade the Highway 32 on and off ramps and construct 14' high sound walls starting at about 250' inside the park's north boundary (about halfway between Vallombrosa Ave. and Petersen Drive) extending to East 1st Ave.

The project is managed by Caltrans, with the Butte County Association of Governments (BCAG) acting as the interface to the public. For background information, see BCAG. On the BCAG web site, you can sign up to receive email or mailed project updates.

A public meeting was held on August 31st, 2011 to answer questions about the Phase Two construction. Our notes from that meeting are available here.

Highway 99 construction photo Construction underway, Sept. 26, 2011
Highway 99 construction photo Park users wait to get past construction equipment. Nov. 9, 2011 — photo by Karen Laslo
Highway 99 construction photo Part of the area to be cleared and covered over by the new auxiliary lanes. Aug. 20, 2011
Highway 99 construction photo Trees cleared from the area. Sept. 20, 2011 — photo by Karen Laslo
Highway 99 construction photo Absorbent boom across Big Chico Creek at site of hydraulic oil spill. Sept. 29, 2011 — photo by Karen Laslo

Creative Commons License
Unless otherwise noted, this site is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 3.0 Unported
by: Friends of Bidwell Park